Weekly Report 3

9/24/2012

 
Current status of project: The project is still in the planning phase. We have assigned sections of the paper to each group member and are making the PowerPoint for our presentation.

Work completed in the last week:  We completed a preliminary design for the spring-loaded locking mechanism and have sent the design to our client for feedback. We have also reviewed the video of the procedure our client sent and have performed preliminary patent and literature searches.

Work planned for next week: We plan to finish our literature search and produce preliminary 3D models of the instrument in Autodesk Inventor.

Anything needed from client or TA or instructor to continue work: Feedback from client on preliminary designs and more specific design constraints.